I had 25 years on the tools as a bricklayer the majority on price work.And the power stations were no better ( the old CEGB), subcontractor on these for over thirty years.
Before nat power/ powergen and the rest, CEGB fitter, fitters mate and an apprentice just to take a 6 bolts off a flange. Nowadays 1 man,( not necessarily a fitter, it's all multitask, ) 2 flanges a valve a bit of welding, all to be done yesterday. Back then they didn't care, it was public money.
Worked on contracts in power stations,steelworks,pits I saw what went off it couldn't carry on like that.
I've run my own firm for 20yrs the majority of my men are on price work.
Incentive works.